(Completion is currently estimated for September/October 2019)

 

View of the link from Block B to Block C. Link block concrete frame complete, Block C concrete frame 2 weeks from completion.

 

 

 

 

 

 

 

 

Block B topped out – concrete frame complete.

 

 

 

 

 

 

Panoramic view from the roof of Block B.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

It has been a frustrating week for our contractors, high winds and intermittent heavy rain have resulted in our tower crane being restricted from operating. However, they have managed to pour part of the roof section of Block B.