June 2019

Completion of Blocks B and C (Rosemary and Lavender) is currently estimated for October and Block D (Sage) in December

 

*** Please find links below for tax advice for non-UK residents produced by Cripps Pemberton Greenish ***

  1. Non-UK-residents_Sale-of-UK-residential-property_April-2019.pdf
  2. Islamic-finance_April-2019.pdf
  3. Tax-for-non-UK-resident-individuals-and-companies_UK-residential-propert….pdf
  4. Advice-for-people-living-outside-the-UK_Property-in-corporate-ownership_….pdf
  5. Advice-for-people-living-outside-the-UK_Personal-ownership_April-2019.pdf

*** Please find link below for our June newsletter and a list of service providers**

  1. June 2019 Newsletter
  2. List of Service Providers : mortgages – letting agents – sale agents – furniture supply – management services.

 

Dear Customers,

Going forward, rather than the quarterly update, we will be commenting monthly. At long last, we have a formal address for the development being 85 Royal Mint Street, London, E1. The concrete frame of the building was completed a few months ago and all cladding panels are now manufactured, 87% are installed and the remainder are either in transit or on site. There is a huge amount of fit-out works taking place with up to 300 operatives on site daily. Bathrooms – kitchens – underfloor heating – M&E,  are being installed and most of the internal partitioning within Blocks B and C are complete. The swimming pool is currently being water tested and work has commenced in the communal garden areas. The lifts in block B are now available for beneficial use which means the temporary hoist on the side of the building can shortly be dismantled. The lifts in block C will be ready before the end of June. One of our tower cranes will shortly be dismantled as all heavy lifting in the western sections have been completed. Last week, our mains electric supply was connected to the newly built substations. By way of update on the adjoining site, work is progressing well with the remainder of the encapsulation. Coffey’s, being our contractor for these rail works, have back to back weekend rail shutdowns so much of the track side elements are taking place, new lighting, new escape platforms and re-routing some of the cabling. Our contractors are still estimating completion for Blocks B and C for October with Block D being available in December. If this changes, we will immediately update this progress site.

 

Panoramic image so distorted, however, good indication of progress.

 

 

 

 

 

 

 

Plant area on top of Block B.

 

 

 

 

 

 

 

 

 

Balconies – concrete pavers being installed.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Brickwork along the walkway leading from Royal Mint Street to the development reception area.

 

 

 

 

 

 

 

 

Brickwork and blockwork in communal areas.

 

 

 

 

 

 

 

North west corner of the façade with part of the hoarding being removed at the first floor.

 

 

 

 

 

 

 

 

Section of pre-cast passive air vent being lifted into the communal garden area.