January 2019

(Completion is currently estimated for September/October 2019)

 

Just the roof to go onĀ and then block B is topped out.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Under floor heating installation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Interior partitioning installation.

 

 

 

 

 

 

 

 

One of the plant rooms – in the process of being fitted out.

 

 

 

 

 

 

 

 

Communal garden link between Block B and Block C, topped out.

 

 

 

 

 

 

 

View of the Shard and across London from the 12th floor – late evening.

 

 

 

 

 

 

City view from the 12th floor – late evening.

 

 

 

 

 

 


Internal tiling now well underway.

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

 

View of Block B from Block C – 4 internal balconies installed and views will be into and over the garden area.

 

 

 

 

 

 

 

Cladding as viewed from the northern elevation.

 

 

 

 

 

 

 

 

 

Double height commercial unit facing Royal Mint Street and entrance piazza.

 

 

 

 

 

 

 


Brickwork collage.

 

 

 

 

 

 

 

 

Cladding panels being laid out in preparation for installation.

 

 

 

 

 

 

 

Brickwork progressing to the front of the townhouses.

 

 

 

 

 

 

 

First couple of balconies facing Royal Mint Street now installed.

 

 

 

 

 

 

 

Staff canteen – keeping the builders well fed.

 

 

 

 

 

 

 

Some balconies have been installed and more are being delivered daily. This is one of the larger balconies that will front Royal Mint Street.

 

 

 

 

 

 

 


 

 

 

 

 

 

 


 

 

 

 

 

 

 

View into the Tower of London, Tower Bridge, the Mayor’s office and The Shard.

 

 

 

 

 

 

View of the City of London from the 11th floor.

 

 

 

 

 

 

One of the floor plates – level 8.

 

 

 

 

 

 

 

The spider crane that is used to lift the cladding panels.

 

 

 

 

 

 

 

Looking into the courtyard from the front of Block B.