October 2017

?

Rebar formation for pile cage. Concrete to be poured to form capping beam.

?

Ground levels reduced and pile caps exposed on the north easterly side of the site. Piles cropped in readiness for capping beam. Once installed, these beams will take the weight of the steel trusses that will straddle the new encapsulation works. Steel sheet piling installed around the perimeter of the site.

?

Piles being exposed and sheet piling works continuing.

?

Creating header access to main sewer and new link from the attenuation tank.

?

Works begin in existing arches. Floors to be removed and structures to be waterproofed. Each arch is continuously monitored for movement.

?

Re-direction of services which have to be completed prior to on-going encapsulation works.

?

Ducting and historic substructure exposed.

?

Western most DLR retaining wall removed. Concrete flooring being excavated in order to relocate the fire mains and DNO (electricity) need relocating.